What happens when a key person for a contractor resigns while a procurement is still pending? A recent protest decision by the Government Accountability Office, Ashlin Management Group, B-419472.3, Nov. 4, 2021, 2021 CPD ¶ 357, addresses this question. The GAO was asked to consider whether the Department of Labor should have evaluated a prospective contractor’s quotation as technically acceptable and awarded it a task order notwithstanding the known unavailability of one of the awardee’s key personnel during the source selection process. In sustaining this protest, the GAO discussed the offeror’s obligation to disclose to the government its employee’s departure and how the agency should have modified its evaluation of the quotations to account for this new development.
Solicitation
On September 9, 2020, the agency issued a solicitation to federal supply schedule contract holders. The solicitation sought quotations for a vendor to assist the National Office of Job Corps in identifying, developing, and implementing career pathway programming.
The solicitation contemplated issuance of a time-and-materials order for a one-year base period and four one-year option periods. It established that award would be made on a best-value tradeoff basis considering price and the following non-price factors: (1) technical approach; (2) key personnel, staff experience and qualifications; (3) management plan; and (4) past performance. The non-price factors were listed in descending order of importance, and combined were significantly more important than price. Under the second most important factor (key personnel), the solicitation required vendors to describe their “processes for recruiting, retaining, and providing highly skilled qualified personnel,” and advised that the agency would evaluate “the effectiveness” of a vendor’s “proposed plan.”
Award and Protest
In December 2020, the agency selected for award a quotation submitted by Booz Allen Hamilton (BAH). Ashlin protested the award to the GAO. In response to the protest, the agency notified the GAO of its intent to take corrective action, committing to reconsider quotations and make a new award decision. This action resulted in a dismissal of the protest as academic.
Upon reconsideration, the agency reevaluated the BAH quotation along with three other technically acceptable, lower rated and higher priced quotations (including the Ashlin quotation). It concluded that none of these three quotations, had any “unique features… that provided better value based on non-price factors,” and that on the basis of non-price factors alone BAH provided better value. The agency found that BAH’s quotation clearly provided better value when considering both the non-price factors and BAH’s lower price, and again selected BAH’s quotation for award.
Ashlin submitted a supplemental protest of the second award to BAH. In this supplemental protest, it noted that the solicitation established three key personnel positions — project director, project manager, and senior project specialist. The protester contended that the person quoted by BAH to fill the senior project specialist key position resigned from BAH’s employ during the corrective action period. The protester maintained that due to this employee’s resignation, BAH had actual knowledge of the unavailability of one of its key personnel, and was obligated to notify the agency.
Legal Authority
In addressing the effect of the departure of one of the awardee’s key personnel, the GAO explained that vendors are obligated to advise agencies of material changes in proposed staffing, even after submission of proposals or quotations. MindPoint Group, LLC, B-418875.2, B-418875.4, Oct. 8, 2020, 2020 CPD ¶ 309. A contractor may not properly receive award of a contract based on a knowing material misrepresentation in its offer. M.C. Dean, Inc., B-418553, B-418553.2, June 15, 2020, 2020 CPD ¶ 206. An offeror or vendor generally is required to advise an agency when it knows that one or more key employees have become unavailable. Id. The duty to notify does not arise, however, if an offeror or vendor does not have actual knowledge of the employee’s unavailability. DZSP 21, LLC, B-410486.10, Jan. 10, 2018, 2018 CPD ¶ 155.
When an agency is notified of the withdrawal of a key person, it has two options: either evaluate the proposal or quotation as submitted without considering the resume of the unavailable employee (in which case the proposal or quotation would likely be rejected as technically unacceptable for failing to meet a material requirement); or open discussions to permit the offeror or vendor to amend its proposal or quotation. M.C. Dean, Inc., supra.
Protest Decision
In defense of the supplemental protest, BAH maintained that the departed employee might be rehired. It recited that it had no knowledge that the resigned senior project specialist would reject an offer of rehiring. The agency similarly maintained that just because the senior project specialist was not currently employed by BAH, this did not necessarily Legal Insights: Departure of Winning Bidder’s Key Person During Source Selection Requires Reevaluation of Award Legal Insights mean that the employee would not agree to return to work under the contract.
The GAO found the argument that BAH lacked actual knowledge of its senior project specialist’s unavailability to ring hollow. To the contrary, the facts were that the senior project specialist submitted a letter of resignation and left BAH’s employ the following month, providing BAH with actual knowledge of the employee’s unavailability. Thus, the GAO concluded that prior to completion of the agency’s source selection process, BAH had actual knowledge that one of its quoted key personnel was unavailable.
The GAO decided that BAH had an obligation to inform the agency of the unavailability of this person, which it did not do. Accordingly, the protest was sustained. The GAO recommended that the agency either evaluate BAH’s quotation as submitted, without considering the previously quoted senior project specialist, or open discussions with all vendors, allow for revised quotations to be submitted, and then make a new source selection decision based on the reevaluation.
Lessons to be Learned
In service contracts it is almost always the case that “people are the product.” In such settings, prospective contractors need to be especially aware that (1) the departure of key personnel during the source selection process must be disclosed to the agency, and (2) this disclosure may very well endanger an award of the contract to the disclosing offeror. It follows that offerors ought to be as confident as possible their key personnel are committed to staying on board should a contract award be forthcoming. Unfortunately, such confidence can be elusive as employees commonly do not share their plans to seek greener pastures until their two weeks’ notice is tendered. A back-up strategy may be to build redundancy into proposals that allow for more than one key person to be available to perform each critical task. Another alternative is to be prepared in advance to quickly replace a key employee headed out the door.
If you have any questions regarding this client alert or how a key person's resignation may affect your contract proposals, please contact Ross Crown at rcrown@lewisroca.com.
Tags: Government ContractsAbout This Blog
Lewis Roca is immersed in your industry and invested in your success. We share insights and trends that can affect your business.
Search
Topics
Archives
- September 2024
- August 2024
- May 2024
- March 2024
- February 2024
- September 2023
- April 2023
- March 2023
- February 2023
- December 2022
- November 2022
- October 2022
- September 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- January 2022
- December 2021
- November 2021
- October 2021
- September 2021
- August 2021
- July 2021
- June 2021
- May 2021
- February 2021
- January 2021
- December 2020
- October 2020
- September 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- March 2020
- February 2020
- January 2020
- December 2019
- November 2019
- October 2019
- September 2019
- August 2019
- July 2019
- June 2019
- May 2019
- April 2019
- March 2019
- November 2018
- April 2018
- February 2018
- January 2018
- December 2017
- November 2017
- September 2017
- August 2017
- June 2017
- May 2017
- April 2017
- March 2017
- November 2016
- October 2016
- September 2016
- August 2016
- April 2016
- January 2016
Authors
- Alfredo T. Alonso
- Amy E. Altshuler
- Edwin A. Barkel
- Trevor G. Bartel
- Nick Bauman
- G. Warren Bleeker
- Brooks Brennan
- Ogonna M. Brown
- Chad S. Caby
- John Carson
- Rob Charles
- Joshua T. Chu
- Howard E. Cole
- Katherine Costella
- Thomas J. Daly
- Pat Derdenger
- Thomas J. Dougherty
- Susan M. Freeman
- Yalda Godusi Arellano
- John C. Gray, CIPP/US
- Art Hasan
- Frances J. Haynes
- Dietrich C. Hoefner
- Jennifer K. Hostetler
- David A. Jackson
- Andrew Jacobsohn
- Kyle W. Kellar
- Kris J. Kostolansky
- Gregory S. Lampert
- Shaun P. Lee
- Glenn J. Light
- Laura A. Lo Bianco
- Karen Jurichko Lowell
- James M. Lyons
- H. William Mahaffey
- Constantine Marantidis
- A.J. Martinez
- Patrick Emerson McCormick, CIPP/US
- Michael J. McCue
- Lindsay L. McKae
- Linda M. Mitchell
- Gary J. Nelson
- Rachel A. Nicholas
- Laura Pasqualone
- Michael D. Plachy
- David A. Plumley
- Kurt S. Prange
- Katie M. (Derrig) Rios
- Robert F. Roos
- Karl F. Rutledge
- Daniel A. Salgado
- Mary Ellen Simonson
- Susan Strebel Sperber
- Jan A. Steinhour
- Ryan M. Swank
- Dustin R. Szakalski
- Chris A. Underwood
- Jennifer A. Van Kirk
- Hilary D. Wells
- Drew Wilson, CIPP/US
- Karen L. Witt
- Meng Zhong
Recent Posts
- The Importance of Retaining a Grandfathered Gaming Location in Nevada
- Welcome our 2024 Michael D. Nosler Scholarship Intern
- Going Viral: Navigating Promotional Sweepstakes Legality in the Social Media Era
- Arizona Voters Modify Creditors' Remedies with Passage of Proposition 209
- Nevada Gaming Control Board Issues Gaming Technology Approval Guidelines
- Amendments to Nevada Gaming Regulation 5
- Nevada Gaming Control Board Workshop on Public Regulation
- New Wave of Arizona Privacy Litigation Regarding Tracking Pixels
- Legal Issues, Problems, and Unanswered Questions Regarding a State’s Ability and Potential Departure from the Depository Institution Deregulation and Monetary Control Act of 1980 (“DIDMCA”)
- New Trademark Scam